Administrative Services
Procedure 519
ADD/MOVE/CHANGE SERVICE REQUEST PROCEDURE
Download a pdf version
of the form here.
Relocation, additions, and changes or District facilities
concern many seemingly unrelated District operations. This procedure is not
intended to hinder the process, but rather. allow for sufficient notification,
input, and coordinated planning with the other areas which are ultimately involved
in the project.
Prior to approval of an add/move/change project, the following
steps shall be implemented to make certain that all parties affected by the
proposed project have been contacted at the appropriate time.
- The requesting Dean/Director shall initiate an Add/Move/Change
Service Request form (see attachment), completing Section 1. If the
add/move/change service request involves a division (or divisions) other than
the initiator's, the requesting Dean/Director shall review the proposal with
the affected division's Dean/Director prior to submitting the form to the
Area Vice President for signature (Section 1).
- The appropriate Vice President shall review the initial
request and approve or deny the request.
- Upon approval, the Dean/Director shall contact the area
administrator (s) directly involved with the project issues enumerated in
Section 2. There may be additional items to be addressed. depending upon the
nature of the project. Once questions have been posed and answered and/or
the appropriate Work Orders have been initiated by the requester, and cost
estimates have been determined, the various administrators involved will "sign
off " for their respective area (s) in Section 2.
- Section 3 is a (partial) checklist designed as a reminder
to inform appropriate campus personnel and District functionaries following
completion of the project. The list may be amended as necessary.
- Section 4 is considered the final approval requirement
for the project, including Cabinet approval, .Area Vice President approval,
total cost estimate, and applicable account code(s) for project expenditures
.
Cabinet approved: 01/09/89